Stevenage, in numbers

Projects: Stevenage

Stevenage local authority area. Every figure carries its own date.

The local plans, investments and decisions worth following.

4 selected records checked against official sources. A plan is not a completed project; each record shows the stage its source establishes.

King George V Park

King George V Park PlayZone

A floodlit sports pitch is being built on part of a disused tennis court.

Work begun; November 2026 completion forecast · evidence dated 2026-10-07

Responsible body: Stevenage Borough Council

What the source says: Completion and actual use are not yet confirmed.

Next thing to establish: What is the approved cost, including ongoing maintenance?

Progress, funding and source
Cost
Not established by the evidence checked.
Funding
Not established by the evidence checked.
Area covered
Named scheme or programme area only. No official impact boundary has been matched to current wards; a nearby location is not evidence that a whole ward benefits.

No verified ward footprint is assigned.

PlayZone construction begins →

Source checked 2026-10-17. A plan or announcement is not proof of completion.

Questions for the next progress report

  • Which funding is committed, and what remains conditional?
  • Which neighbourhoods are covered by an official project plan, and which benefits still need testing?
  • What is the next published milestone, and what evidence will show residents benefit?

Make the new pitch affordable to use →

Target support where disadvantages overlap →

How to track delivery →

St Georges Way, Stevenage

New sports and leisure centre

A new building will bring together pool and sports facilities, with temporary changes to parking access.

Construction programme announced March 2026 · evidence dated 2026-03-12

Responsible body: Stevenage Borough Council

What the source says: The council reports construction beginning; the 2028 parking reopening is a forecast.

Next thing to establish: What is the approved cost, including ongoing maintenance?

Progress, funding and source
Cost
Not established by the evidence checked.
Funding
Not established by the evidence checked.
Area covered
Named scheme or programme area only. No official impact boundary has been matched to current wards; a nearby location is not evidence that a whole ward benefits.

No verified ward footprint is assigned.

Sports centre construction and access →

Source checked 2026-10-17. A plan or announcement is not proof of completion.

Questions for the next progress report

  • Which funding is committed, and what remains conditional?
  • Which neighbourhoods are covered by an official project plan, and which benefits still need testing?
  • What is the next published milestone, and what evidence will show residents benefit?

Protect access during sports-centre construction →

Target support where disadvantages overlap →

How to track delivery →

Stevenage railway station and surrounding area

Station Gateway development agreement

The council and development partners agreed to prepare a major station-area scheme with homes and public spaces.

Development agreement signed; masterplanning stage · evidence dated 2026-01-12

Responsible body: Stevenage Borough Council

What the source says: The proposed 2028 start and 2030 first homes depend on securing government grant funding.

Next thing to establish: What is the approved cost, including ongoing maintenance?

Progress, funding and source
Cost
Not established by the evidence checked.
Funding
Not established by the evidence checked.
Area covered
Named scheme or programme area only. No official impact boundary has been matched to current wards; a nearby location is not evidence that a whole ward benefits.

No verified ward footprint is assigned.

Station Gateway development agreement →

Source checked 2026-10-17. A plan or announcement is not proof of completion.

Questions for the next progress report

  • Which funding is committed, and what remains conditional?
  • Which neighbourhoods are covered by an official project plan, and which benefits still need testing?
  • What is the next published milestone, and what evidence will show residents benefit?

Keep Station Gateway milestones conditional →

Make room for homes people can afford →

Connect local skills to local opportunities →

Target support where disadvantages overlap →

How to track delivery →

Across Stevenage

Rough-sleeper support and Housing Futures

Outreach and referrals are supplemented by a small accommodation service with ongoing support.

Service operating; places limited · evidence dated 2026-04-24

Responsible body: Stevenage Borough Council

What the source says: Eligibility is assessed individually and the programme has very limited capacity.

Next thing to establish: What is the approved cost, including ongoing maintenance?

Progress, funding and source
Cost
Not established by the evidence checked.
Funding
Not established by the evidence checked.
Area covered
Named scheme or programme area only. No official impact boundary has been matched to current wards; a nearby location is not evidence that a whole ward benefits.

No verified ward footprint is assigned.

Street homeless services →

Source checked 2026-10-17. A plan or announcement is not proof of completion.

Questions for the next progress report

  • Which funding is committed, and what remains conditional?
  • Which neighbourhoods are covered by an official project plan, and which benefits still need testing?
  • What is the next published milestone, and what evidence will show residents benefit?